Two members of the public injured following uncontrolled structural collapse during site preparation for demolition works (3 August 2026)
During site preparation activities for demolition work, an unplanned partial collapse of a structural wall and roof occurred.
This resulted in a significant amount of debris falling into an adjacent car park, causing injuries to two members of the public.
The uncontrolled nature of the structural collapse highlights the significant risks associated with demolition works, including site preparation.
Safety information
Consider ‘reasonably practicable’ control measures to manage the risks associated with uncontrolled structural collapse and falling objects during site preparation and demolition works.
Ensure:
- demolition works are completed by trained and licensed PCBUs in accordance with WHS legislation
- hazards associated with site preparation activities, including with demolition works, are identified and controlled
- a Safe Work Method Statement (SWMS) is prepared and followed for all high risk construction work, including for mobile plant
- the demolition licence holder notifies SafeWork NSW at least five calendar days before starting any demolition work
- the licence holder, in consultation with a competent person and all relevant stakeholders, prepares a site-specific demolition control plan before work begins
- the demolition plan includes the sequence of demolition activities and identifies structural components
- the demolition plan addresses public safety, especially in areas adjoining the workplace, for example roads, car parks and walkways
- workers and plant operators engaged in demolition follow the demolition sequence as detailed in the demolition plan
- when planning demolition work, plant selected is suitable for both the structure and work to be undertaken
- the demolition licence holder prepares a site-specific (SWMS) before starting demolition work and consultation is undertaken directly with all relevant persons and workers who will be carrying out the demolition work.
Related guidance material
- Construction work: Code of practice (PDF, 1014.41 KB) – SafeWork NSW
- Demolition work: Code of practice (PDF, 668.8 KB) – SafeWork NSW
- Overhead protective structures: Code of practice (PDF, 549.32 KB) – SafeWork NSW
- Wall collapse: Incident information release – SafeWork NSW
- Demolition – SafeWork NSW
- Falling objects in construction fact sheet (PDF, 122.91 KB) – SafeWork NSW
- AS/NZS 2601: The demolition of structures
Further information
- Traumatic event management plan – SafeWork NSW
- Speak Up Save Lives app – SafeWork NSW
- Mental health at work – NSW Government
- Subscribe to SafeWork NSW newsletters and updates